Railway Accounts Department Examinations

Showing posts with label Departmental charges. Show all posts
Showing posts with label Departmental charges. Show all posts

Wednesday, May 17, 2023

Departmental charges ( D&G charges )

 


Departmental Charges ( D&G Charges ) in Works Estimates 


  • Sources: 1. Railway Board Letter No. 2022/E&R/3(2)/1 dated 28.12.2022 Click here

    2. Railway Board Letter No. 2018/E&R/3(2)/1 dated 04.03.2020 Click here 

    3. Para 1120 of IR Engineering Code 

 

  • A committee was constituted at the Railway Board level to review the D&G charges thoroughly for various Works Estimates.  


  • Based on the recommendations of the Committee, the following changes have been effected vide letter under Source No. 1 above. 

 

  • Departmental Charges - New term in place of D&G Charges  

 

  • D&G Charges stands for Direction & General Charges 


  • Will cover - Both i.e., Departmental manpower and Hired manpower of Projects (including Revenue posts)

 

  • Electrical and S&T Works  - Distinction of “With & Without Block” works removed. 

 

  • Consists of the Establishment portion only.  

 

  • Not included: The cost of Pay & Allowances of Land Acquisition Staff.  Because the same is included in the Sub estimate of Land Acquisition as part of the Project.  

 

  • Other than the Establishment portion  -Removed.  However, ERW & Sports Development Fund are continued.    

 

  • Gazetted posts - Not more than 50%  




% Ceiling of Departmental Charges for Various Works  


Projects

Percentage - Departmental Charges

Civil Engineering

5.32 %

Track Renewal Works (Primary & Secondary)

1.53 %

Electrical Projects (incl: RE)

7.15 %

S & T 

10.04 %

Mechanical

4.91 %


Note: Break up of the above percentages among various Departments as per the Railway Board Letter dated 28.12.2020 (Annexure-II)


ERW: 

 

  • ERW stands for Environmental Related Works  

  • 0.5 % provision of the overall value of the Estimate including Contingency 1%. (Example: If the Estimate value is Rs.100, the ERW provision is Re 0.50)

  • Applicable to Plan Heads 11, 14, 15, 30 & 42 only 

  • Not applicable - If the works under the above Plan Heads are funded through EBR(IF) 

  • EBR(IF) stands for Extra Budgetary Resources (Institutional Finance) 

  • If the work is specifically for Environment Management, it should be processed for sanction as Itemised Work 


Sports Development Fund: 

 

  • Object: To create a robust Sports infrastructure in tune with IR Sports contribution

  • 0.1 % provision of the overall value of the Estimate including Contingency 1%. (Example: If the Estimate value is Rs.100, the Sports Development Fund provision is Re 0.10) 

  • Applicable to all Plan Heads {Except Plan Heads 17 & 31 and Projects funded through EBR(IF) }

  •   If the work is specifically for Sports Development, it should be processed for sanction as Itemised Work 



Contingency:  

 

  • Uniform 0.1 % - shall be part of the Estimate.  (Example if the Total Estimate value is Rs.100, the provision of Contingency is Re. 1)

  • Provision for contingency - Should not be diverted to any new work or repair which is not provided in the estimate.  If so, it should require the sanction of the authority who sanctioned the estimate. If the Sanctioned authority is beyond GM, the GM Can sanction.  

  • The contingency portion of Departmental charges is removed.   

  • Used only for Unforeseen items essentially required for completing the Project.  

  • Included: Cost of Project specific training, if not covered in the Detailed Estimate. 


 

Example of Calculation of:   



  • The Project Estimate Cost - Rs. 50000.  The calculation of :  



Item

Calculated Amount

Remarks

Contingency

Rs. 500

@ 1 % of the Estimate Value.  Part of the Estimate

ERW

Rs. 250

@ 0.5 % on the Total Estimate value.


Worked out on the overall value of the Estimate including Contingency i.e., 0.5 % on Rs.50000

Sports Development Fund

Rs. 50

@ 0.1 % on the Total Estimate value.


Worked out on the overall value of the Estimate including Contingency i.e., 0.1 % on Rs.50000

 


Key points for MCQ 


  1. Calculation of the Contingency is Part of the Estimate, whereas of ERW & Sports Development Fund is on the overall value of the Estimate. 

  2. Departmental charges - New name of D&G charges 

  3. D&G charges stand for Direction & General charges 

  4. Departmental charges - Cover - Both Departmental Manpower and Hired Manpower including Revenue posts. 

  5. Consists of the Establishment portion only.  The non-Establishment portion was removed.  

  6. Gazetted posts - Not more than 50% 

  7. ERW stands for Environmental Related Works 

  8. Sports Development Fund - 0.1 %, ERW - 0.5 %, and Contingency - 1 % 

  9. ERW and Sports Development Fund - Not applicable for Projects funded through EBR(IF) 

  10. EBR(IF) stands for Extra Budgetary Resources (Institutional Finance) 

  11.  ERW - Applicable to Plan Heads 11, 14, 15, 30 & 42 only. 

  12.  Sports Development Fund - Applicable to all Plan Heads (except 17 & 31) 



—--end—-


Saturday, June 1, 2019

Deposit Works And Departmental Charges

Deposit Works

And

 Departmental Charges

Ø  Source: 18th chapter of Engineering Code

 

Ø  Definition – The works which are executed by Railways for other Govtdepts, private firms or individuals.  So the cost is met from non-railway sources.

 

Ø  In simple, the works, the cost is met from other than railway funds are called as Deposit works.

 

Ø  Examples of Deposit Works  

 

1)    Level Crossing required by the canal dept 10 years after the opening of line

2)    culvert required by the Irrigation dept or a private individual

3)    Electric/telephone wires required to be laid by Electric supply co or Telephone company over or under Railway line.

 

Ø  The concerned Dept/private firm/individual should approach the Railways for work executed duly furnish a rough sketch of the work & other relevant particulars.

 

Ø  If agreed to execute such Deposit works by Railways:-

 

1.   Other Govt Depts – should accept the charges leviable to meet the cost of plans and estimates of the required works.

 

2.   Private parties – should deposit the charges leviable to meet the cost of plans and estimates of the required works with the Railways.  However such charges (cost of plans & estimates) should be adjusted against the Departmental Charges, in case, the proposed works are subsequently carried out.

 

Ø  After obtaining the acceptance or cost of the plans and estimates has been deposited with the Railways, the detailed plans & estimates of the required works should be prepared and got accepted by the applicants.

 

Ø  As and when excess is anticipated, the same should be intimated to the concerned parties and got acceptance/deposit the excess charges as the case may be. 

 

Departmental Charges : These charges should be levied to cover the cost of tools & plant and of establishment supervision.  These charges levied at 12.5% on the total cost of the Deposit work (wages & material) include the cost of land.

 

Ø  Booking of expenditure: The amount deposited by the private parties should be credited to the “Deposit Misc” and the expenditure incurred on the said Deposit works should be charged/debited to the same Head “Deposit Misc”.

 

Ø  A separate register of Works should be maintained for all Deposit works in a Division.  Separate account should be kept for each Deposit work in that Register.  The postings in this Register should be totaled up and reconciled with the General Books monthly.  In case of works undertaken for other govt depts., suitable remarks as to the amounts adjusted monthly should be given in the register.  In case of private parties, the amount should be reconciled with the “Deposit Misc” head monthly and a certificate of reconciliation recorded in the register.

 

Ø  As and when anticipate the expenditure exceeds sanctioned estimate or sanctioned allotment of deposit made, the Executive Engineer should prepare the Revised Estimate and got sanctioned by the competent authority.

 

Ø  Completion:  on the completion, an intimation of the date of completion should be sent to the Accounts officer. Completion report in Form E1706 should be prepared showing the variations of actual expenditure with the sanctioned estimate and furnished to the party for whom the work was executed. Unexpended balance lying at the credit of “Deposit Misc” should be refunded to the party.

 

Ø  Model of “Deposit Misc” Suspense head. The balance of this Head always Credit balance.

 

Deposit Misc A/c

Debit

Credit

Date

Particulars

Amt(Rs)

Date

Particulars

Amt(Rs)

10.01.2017

Works executed

80,000

01.01.2017

Cash deposited for executing the work

1,00,000

31.01.2017

Refund of unexpended amount

20,000

 

 

 

 

Total

1,00,000

Total

 

1,00,000

Maintenance: All Deposit works in Railway premises should be maintained by the Railway administration at the cost of parties who applied for them.  Such maintenance charges should be recovered as follows.

(1) either a fixed percentage of the works, the rate being fixed by the General Manager.

(2) or actual expenditure (including departmental charges).

Ø  The Accounts Officer is responsible for recovery of Maintenance & other charges.

Deposit Works – SPV (Special Purpose Vehicle) having Govt participation

Ø  20 % of the estimated cost to be deposited initially, if the work is Rs. 3 Lakhs or more.

Ø  It is treated as Revolving Fund.  Replenished from time to time at a frequence of 2 weeks/monthly/quarterly intervals.

Ø  Replenishment through Letter of Credit also allowed. The Period should be at least one year after the completion of works.

 

Departmental Charges:

Ø  Source: 1137E

Ø  Rate: 12.5 % on the cost of Deposit Work (Wages & Material and cost of land, if any)

Ø  In case any other Dept levied Departmental charges are more than 12.5 %, the same is charged on reciprocal basis.

Ø  To cover the cost of tools & plant and the establishment supervision.

Ø  These charges should be levied to cover the cost of tools & plant and of establishment supervision.  These charges levied at 12.5% on the total cost of the Deposit work (wages & material) include the cost of land.

Ø  The above rules do not apply to works of ROB/RUB in replacement of existing manned LC Gates taken up on BOT (Build, Operate & Transfer) basis.

Remission of Departmental Charges (1138 E)

Ø  The GM may, at his discretion, waive wholly or partially, provided that

 

1.   The Railway gains some advantage, not necessarily financial, by such remission.,

2.   The reasons for such remission are recorded in each case

3.   Concurrence of PFA

4.   Non incurrence of extra charges on account of tools & plants and establishment supervision does not in itself constitute sufficient justification for such remission.

 

Ø  In case of Assisted or Private sidings:

 

1.   When a portion of the work is permitted to be executed by parties, partial remission of departmental charges may be allowed.

2.   Up to Rs. 10 Lakhs.

3.   If the parties apply for further remission (beyond Rs. 10 Lakhs), a reference should be made to the Railway Board

 

#####