RSP - Road Safety Projects - PH 30 - ROB / RUB - New Vertical
Authority: Railway Board Letter No. 2024/CE-IV/ROB-RUB/SCR, WR, ECR & NR dated 07.05.2024
Object of New Vertical: Execution of ROBs/ RUBs has not kept pace with the pace of new sanctions being given.
New Vertical - CAO/Con/RSP - Exclusively for Road Safety Projects - for Road Crossing Works i.e., PH 29 - Level Crossings and PH 30 - ROB / RUB
RSP stands for Road Safety Projects (RSP also Rolling Stock Programme)
Salient features of RSP:
RSP vertical - headed by CAO/Con/RSP who is in HAG - Higher Administrative Grade
Assisted by SAG/Engineering Dept, other officers and staff
Reporting directly to GM
Associated Finance: FA&CAO/Con
GC - General Consultant: engaged by CAO/Con/RSP for holistic planning of RSP works incl: Feasibility studies (new name for Surveys), DPR preparation, Sanction of Work, detailed structural design, detailed estimate & engagement of PSSA/PMS/PMC
EPC / Hybrid mode EPC / BOQ based Contracts - for execution of RSP
Nodal Directorate for RSP : Bridge Directorate in Railway Board
CAO/Con/RSP: Execution in-charge of RSP
CAO/Con/RSP & his Officers will exercise the powers of Construction organisation as per MSOP (in respect of all Technical, Financial, Contractual & Personnel matters)
PCE: Monitoring and overall coordination for RSP
Key points of RSP:
RSP - New Vertical for PH 30 - ROB / RUB
RSP headed by HAG Officer (of Engineering Dept)
Reporting directly to GM
Associated Finance: FA&CAO/Con
Nodal Directorate: Bridge Directorate (in Railway Board)
PCE: Overall coordination of RSP
Abbreviations:
RSP - Road Safety Works
RSP - Rolling Stock Programme
ROB - Road Over Bridge
RUB - Road Under Bridge
CAO - Chief Administrative Officer (HAG rank)
HAG - Higher Administrative Grade (PHOD rank)
PHOD - Principal Head Of Department (HAG rank)
PCE - Principal Chief Engineer (HAG rank/PHOD)
SAG - Senior Administrative Grade
GC - General Consultant
DPR - Detailed Project Report
PSSA - Project Supervision Services Agency
PMS - Project Management System
PMC - Project Management Consultancy
EPC - Engineering Procurement & Construction
BOQ - Bill Of Quantities
MSOP - Model Schedule Of Powers
&&&&