Secunderabad Railway Station - Redevelopment
Objects:
Redevelop and regenerate city core area by the redevelopment of Railway Station.
Multi-modal integration and the seamless transfer of passengers from one mode to another mode.
Generate business opportunities and revenue generation for the local body too.
Floated Tender for redeveloping the Secunderabad Railway Station (June 2022)
Estimated cost - Rs. 653 Crores
Executed on EPC mode. (Engineering Procurement & Construction ). The bidder is responsible for designing, Procuring the equipment or machinery, and Constructing and commissioning the project.
Target period : 3 Years from the date of award of the Tender.
Zonal Railway (SCR) is the responsibility as IRSDC is closed by the Indian Railways.
North side of Railway Station - 22516 Square meters - G + 3 floors
South side of Railway Station - 14792 Square meters - G + 3 floors.
Multi-level parking - 5 levels the north of Railway Station
Special entry and exit lanes (drop off and pick up ) separately.
5000 kv solar power plant.
Double storey sky concourse of 108 meters in width. First-tier for passengers and Second tier for the Public as a rooftop plaza of 24604 square meters.
Two travelators (walkways) at Southside (Main Building) and North Side.
Connecting with skyway of East and West Metro (Hyderabad Metro) Stations.
******